Construction updates for the CC-Ⅰ building will be posted here on weekly basis

Summary:
  • Formwork: Ironstone Formwork
  • Mechanical: J & S Mechanical
  • Electrical: Nortown Electric
  • Waterproofing: Torrent
Construction Images
***
Summary:
  • Pour 01: GF Concrete placing
  • Pour 02: GF Rebar placing
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
Construction Images
Overview of Ground Floor formwork
Construction Images
Site overview from west wall
Construction Images
Northwest corner formwork and rebar placing on Pour 01
Construction Images
Partial backfilling on exterior of south wall
Construction Images
Ground floor Pour 04 and 06
Construction Images
Rebar placing on Pour 02 GF
Construction Images
Ground Floor Pour 01 formwork and rebar
Construction Images
Ground Floor and P1 Pour 06
Construction Images
Overview of Ground Floor Pours 02 and 04
Construction Images
Ground Floor Pour 02 Rebar and electrical conduits
Construction Images
Ground Floor Pour 02 top rebar placing
Construction Images
Bobcat hoisted for ground floor work
Summary:
  • Pour 01: GF Concrete placing
  • Pour 02: GF Rebar placing
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
Construction Images
***
Summary:
  • Pour 01: GF Framework and rebar placing
  • Pour 02: GF Formwork and rebar placing
  • Pour 03: Columns and Walls pouring
  • Pour 04: GF Formwork
  • Pour 05 & 06: Vacuum & Shoring outside south wall
Construction Images
Installation of protection board on north wall
Construction Images
Electrical rough-ins on Pour 01 GF
Construction Images
Plumbing rough-ins on Pour 01 GF
Construction Images
Application of protection board on east wall
Construction Images
Rebar placing on Pour 02 GF
Construction Images
Ongoing formwork on Pour 04 GF
Construction Images
Placing of top bar on Pour 01 GF
Construction Images
Beam placing on Pour 02 GF
Construction Images
Overview of Pours 03 and 04 GF
Construction Images
Overview of Pours 02, 03 and 04 GF
Construction Images
Pour 01 rebar and formwork GF
Construction Images
Overview of GF from Northwest corner
Construction Images
Overview of Southwest corner
Construction Images
Overview of Pour 01 GF top rebar placing
Construction Images
Top rebar placing on Pour 01 GF
Summary:
  • Pour 01: GF Framework and rebar placing
  • Pour 02: GF Formwork
  • Pour 03: Columns and Walls pouring
  • Pour 04: Walls on GF/P1 ramp
  • Pour 05: Walls and Columns pouring
  • Pour 06: Vacuum & Shoring outside south wall
Construction Images
Overview of pours 04, 05 and 06
Construction Images
Pour 04 formwork
Construction Images
Pour 01 formwork and beam rebar
Construction Images
Pour 01 breezeway beam rebar
Construction Images
Pour 02 Formwork
Construction Images
North wall waterproofing
Construction Images
Chiller installed on P1, Pour 01
Construction Images
Pour 01 Rebar and Electrical rough-ins.
Construction Images
Pour 01 rebar on breezeway
Construction Images
Pour 01 Electrical Rough-ins