Construction updates for the CC-Ⅰ building will be posted here on weekly basis

Summary:
Formwork:
  • Concrete Parging on P1/P2 level
  • Formwork, rebar and concrete of southwest ground floor Air shaft
  • Concrete P2 level on crane pad
Mechanical:
  • Install RWL on South perimeter wall
  • Installation on Mechanical room
Electrical:
  • Pulling wires on P1 and P2
  • Electrical room preparation
Masonry:
  • Ground Floor walls on Stair-01 and Intake Air shaft – ongoing
  • Air Supply Shaft and Elevator ground floor walls – to be started
Construction Images
***
Summary:
Formwork:
  • Retaining wall along driveway on Pour 05 ground floor
  • Ongoing concrete parging
  • Housekeeping pads on mechanical room
Earthworks:
  • Backfilling of building perimeter
Mechanical:
  • Pipe laying on P1 and P2
  • Installed RWL on east perimeter wall
Electrical:
  • Pulling wires on P1 and P2
  • Rough-ins on masonry walls
Masonry:
  • Ground Floor walls on Stair-01 and Intake Air shaft – ongoing
Construction Images
Shotcrete on East Elevation wall
Construction Images
Shotcrete on driveway east retaining wall
Construction Images
Rebar and formwork on west wall
Construction Images
Overview of Ground floor in P1-GF ramp area and courtyard
Construction Images
Housekeeping pad poured and concrete parging-grinding
Construction Images
Backfilling in progress, with installation of fabric
Construction Images
South wall backfilling
Construction Images
Installation of waterproofing drainage board
Construction Images
East elevation prior to backfilling
Construction Images
East elevation backfilling
Construction Images
Mechanical installation on P1 level
Construction Images
Mechanical installation on P1 level, Pour 02 and 04
Summary:
Formwork:
  • Formwork, rebar and concrete on elevator divider wall
  • Poured Reveal west wall
  • P1 Level structural parging - ongoing
Mechanical:
  • Pipe laying on P1 and P2
Electrical:
  • Pulling wires on P1 and P2
  • Light fixture installation on Retaining west wall
Masonry:
  • Ground Floor walls on Stair-01 and Intake Air shaft
Construction Images
Formwork_Rebar and formwork on East Elevation wall – feature wall with reveals
Construction Images
Formwork_Overview of Courtyard.jpg
Construction Images
Formwork_Rebar and formwork on west wall
Construction Images
Formwork_Shotcrete with reveals on feature west wall
Construction Images
Formwork_Elevator demising wall on P1 Level
Construction Images
Formwork_Rebar and formwork east of driveway, Ground Floor, Pour 05
Construction Images
Formwork_Elevator demising wall concrete pouring up to Ground Floor
Construction Images
Electrical_Electrical rough-ins on west wall
Construction Images
Masonry_Stair-01 blocks with 1st mid-landing
Construction Images
Masonry_Stair-01 walls, ground floor, Pour 02
Summary:
  • Pour 02: Formwork, rebar and conctete on elevator divider wall
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams.
  • Pour 05 & 06: Perimeter wall parging
  • P1 & P2: Structural parging
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2
Construction Images
***
Summary:
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab concrete
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2
Construction Images
Overview of Ground Floor Pour 05 bottom rebar and cor lines
Construction Images
Overview of Ground Floor Pour 05 bottom rebar
Construction Images
Overview of Ground Floor Pour 05
Construction Images
Ground Floor Pour 04 and 06 overview to courtyard
Construction Images
Ground Floor Pour 02 overview
Construction Images
Ground Floor Pour 05 top rebar on upper slab
Construction Images
Ground Floor Pour 05 top rebar on upper slab
Construction Images
Ground floor Pour 05 overview of concrete pouring
Construction Images
Ground Floor Pour 05 upper slab concrete pouring
Construction Images
Overview of Ground Floor Pours 05 concrete finishing
Construction Images
Ground Floor Pour 05 balcony with cast in place stairs
Construction Images
Ground Floor Pour 05 upper slab bottom rebar
Summary:
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab concrete on driveway area
  • Pour 06: GF slab rebar and concrete
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2
Construction Images
Ramp on P1-GF top concrete poured
Construction Images
View of Ramp P1-GF from driveway
Construction Images
Overview of Ground Floor Pour 03
Construction Images
Ground Floor Pour 05 rebar placing on driveway area
Construction Images
Ground Floor Pour 03 upturn beam north of ramp P1-GF
Construction Images
Ground Floor Pour 03 Concrete pouring on driveway area
Construction Images
Ground Floor Pour 05 and 06 driveway slab
Construction Images
Overview of Ground Floor Pours 03 and 05
Construction Images
Ground Floor Pour 05 upper slab electrical and mechanical rough-ins
Construction Images
Ground Floor Pour 05 Stair landings cast in place
Construction Images
Ground Floor Pour 05 upper slab bottom rebar
Summary:
  • Pour 01 & 02: Concrete on corbels on north wall
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab formwork
  • Pour 06: GF slab rebar and concrete
Construction Images
Ground floor courtyard area, Pours 05 and 06 concrete pouring
Construction Images
Ground Floor Pour 06 overview
Construction Images
Ground Floor Pour 06 rebar placing
Construction Images
Ground Floor Pour 06 bottom rebar
Construction Images
Ground Floor Pour 06 cor-line and rough-ins
Construction Images
Ground Floor Pour 06 top rebar and edge formwork
Construction Images
Ground Floor Pours 05 formwork
Construction Images
Ground Floor Pour 06 concrete
Construction Images
Ground Floor Pour 06 concrete
Summary:
  • Pour 01 & 02: Purging and corbels on north wall
  • Pour 03: Formwork, rebar placing and concrete on loading and commercial garbage
  • Pour 05: GF slab formwork
  • Pour 06: GF slab formwork
Construction Images
Overview of ground floor & installation of fall protection equipment
Construction Images
Ground Floor Pour 04 overview
Construction Images
Ground Floor Pour 03 Loading dock
Construction Images
Ground Floor Pour 03 ramp walls
Construction Images
Ground Floor Pour 05 and 06 lower portion - Courtyard
Construction Images
Ground Floor Pour 03 overview
Construction Images
Ground Floor Pour 02 and 01 overview
Construction Images
Gorund Floor-P1 ramp installation of heating pipe
Construction Images
Overview of Ground Floor Pours 05 and 06
Summary:
  • Pour 01 & 02: Perimeter wall waterproofing
  • Pour 03: Formwork, rebar placing and concrete (finish)
  • Pour 05: GF formwork, rebar and concrete
  • Pour 06: GF formwork
Construction Images
***
Summary:
  • Pour 01 & 02: Formwork, rebar and of cantilevered beam on breezeway
  • Pour 03: Formwork, rebar placing and concrete
  • Pour 05: P1 south wall formwork, rebar and concrete
  • Pour 06: GF formwork
Construction Images
Southeast corner overview
Construction Images
Ground Floor Pour 06 Formwork
Construction Images
Ground Floor Pour 03 catch basin area concrete pouring
Construction Images
P1 Pour 5 South wall formwork & column concrete placing
Construction Images
Pour 03 Ground Floor formwork
Construction Images
P1 Pour 05 Air shaft formwork and rebar
Construction Images
P1 Pour 05 overview of fromwork
Construction Images
Ground floor Pour 03 electrival rough-ins and rebar placing
Construction Images
Ground Floor overview of pours 03 and 05
Summary:
  • Pour 01: GF Rebar placing and Shotcrete northwest wall
  • Pour 02: P1 removal of formwork
  • Pour 03: Formwork and rebar placing
  • Pour 04: GF rebar placing and concrete
  • Pour 05: P1 south wall formwork, rebar and concrete
  • Pour 06: P1 south wall formwork
  • Pour 07: Formwork on GF/P1 ramp area
Construction Images
Pour 04 overview
Construction Images
Courtyard area rebar placing
Construction Images
South wall backfill to P1 level
Construction Images
Rebar on Courtyard
Construction Images
Shotcrete on Pour 01 Northwest corner
Construction Images
Concrete Pouring on Courtyard
Construction Images
P1 Pour 06 south wall rebar
Construction Images
Overview of Ground Floor Pour 04
Construction Images
Pour 04 Ground Floor rebar placing
Construction Images
Mechanical sleeving on Pour 04 Ground Floor
Construction Images
Overview of Ground Floor Pours 03 and 05
Construction Images
Pour 04 Ground floor concrete placing
Construction Images
Pour 04 Ground floor concrete placing
Summary:
  • Pour 01: GF concrete on northwest corner
  • Pour 03: GF Formwork and rebar placing
  • Pour 04: GF Rebar placing – courtyard area
  • Pour 06: Finish GF formwork
  • Pour 07: Concrete on GF/P1 ramp area – bottom portion
Construction Images
Courtyard area formwork
Construction Images
Pours 02 & 04 Ground Floor overview
Construction Images
Rebar on Ramp P1/GF on Pour 03
Construction Images
Overview of Ground Floor Pour 01 & 03
Construction Images
Ground Floor ramp area rebar Pour 03
Construction Images
Overview of Ground Floor pours 03 & 04
Construction Images
Pour 03 Ground Floor rebar placing
Construction Images
Overview of Ground Floor Pour 04 and 06 Courtyard
Construction Images
Overview of Ground Floor Pours 03 and 04
Construction Images
Formwork on Ground Floor Pour 03
Summary:
  • Pour 02: GF Rebar placing and Concrete pouring
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
  • Pour 07: rebar placing on GF/P1 ramp area
Construction Images
Pour 02 Ground Floor rebar placing
Construction Images
Pour 02 Ground Floor top rebar placing
Construction Images
Overview of Ground Floor Pours 03 and 05
Construction Images
Pour 02 Ground Floor formwork on north wall
Construction Images
Ground Floor Pours 01 and 03 west wall
Construction Images
Ground Floor Pour 02 concrete pouring and rebar
Construction Images
Overview of Ground Floor Pour 02 from north
Construction Images
Ground Floor Pour 02 lower elevation
Summary:
  • Pour 01: GF Concrete placing
  • Pour 02: GF Rebar placing
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
Construction Images
Overview of Ground Floor formwork
Construction Images
Site overview from west wall
Construction Images
Northwest corner formwork and rebar placing on Pour 01
Construction Images
Partial backfilling on exterior of south wall
Construction Images
Ground floor Pour 04 and 06
Construction Images
Rebar placing on Pour 02 GF
Construction Images
Ground Floor Pour 01 formwork and rebar
Construction Images
Ground Floor and P1 Pour 06
Construction Images
Overview of Ground Floor Pours 02 and 04
Construction Images
Ground Floor Pour 02 Rebar and electrical conduits
Construction Images
Ground Floor Pour 02 top rebar placing
Construction Images
Bobcat hoisted for ground floor work
Summary:
  • Pour 01: GF Concrete placing
  • Pour 02: GF Rebar placing
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
Construction Images
***
Summary:
  • Pour 01: GF Framework and rebar placing
  • Pour 02: GF Formwork and rebar placing
  • Pour 03: Columns and Walls pouring
  • Pour 04: GF Formwork
  • Pour 05 & 06: Vacuum & Shoring outside south wall
Construction Images
Installation of protection board on north wall
Construction Images
Electrical rough-ins on Pour 01 GF
Construction Images
Plumbing rough-ins on Pour 01 GF
Construction Images
Application of protection board on east wall
Construction Images
Rebar placing on Pour 02 GF
Construction Images
Ongoing formwork on Pour 04 GF
Construction Images
Placing of top bar on Pour 01 GF
Construction Images
Beam placing on Pour 02 GF
Construction Images
Overview of Pours 03 and 04 GF
Construction Images
Overview of Pours 02, 03 and 04 GF
Construction Images
Pour 01 rebar and formwork GF
Construction Images
Overview of GF from Northwest corner
Construction Images
Overview of Southwest corner
Construction Images
Overview of Pour 01 GF top rebar placing
Construction Images
Top rebar placing on Pour 01 GF
Summary:
  • Pour 01: GF Framework and rebar placing
  • Pour 02: GF Formwork
  • Pour 03: Columns and Walls pouring
  • Pour 04: Walls on GF/P1 ramp
  • Pour 05: Walls and Columns pouring
  • Pour 06: Vacuum & Shoring outside south wall
Construction Images
Overview of pours 04, 05 and 06
Construction Images
Pour 04 formwork
Construction Images
Pour 01 formwork and beam rebar
Construction Images
Pour 01 breezeway beam rebar
Construction Images
Pour 02 Formwork
Construction Images
North wall waterproofing
Construction Images
Chiller installed on P1, Pour 01
Construction Images
Pour 01 Rebar and Electrical rough-ins.
Construction Images
Pour 01 rebar on breezeway
Construction Images
Pour 01 Electrical Rough-ins